Perth's oldest wastewater treatment plant, tucked behind Lemnos Street in Shenton Park, is to be expanded so the central and western suburbs can take tens of thousands more homes. The State Government has committed an initial $105 million to the job and Water Corporation is now asking construction companies to help design it.
The plant, officially the Subiaco Water Resource Recovery Facility, has been operating since 1927. According to a Water Corporation media release dated 23 November 2026, it treats about 65 million litres of wastewater a day from around 120,000 homes and businesses in an area stretching from Scarborough to North Fremantle and east to Maylands.
What is planned
The proposed upgrade would lift the plant's treatment capacity by around 23 million litres a day, which is roughly a third more than it handles now. Water Corporation says that would be done by building what it calls a "compact, innovative plant" on the existing Lemnos Street site, not by moving the facility somewhere else.
The $105 million is not the cost of the whole upgrade. The release says it will pay for detailed design and engineering work, site preparation and the early activities needed to get the project moving. No total cost and no construction start or finish date have been published.
The Government says the extra capacity is needed to support up to 60,000 future homes across Perth's central and western suburbs, or housing for more than 135,000 people over the next 25 years. It names Subi East, Belmont Park Racecourse and Fremantle Port as development areas that depend on it.
The smell question
For people who live, work or play sport near the plant, one line in the release will stand out. Water Corporation says the upgrade will improve treatment quality and create more opportunities to recycle water, and that it is "investigating advanced odour control systems as part of the design work".
That is a statement that odour control is being looked at, not a promise of what will be built. What the design ends up including should become clearer once the design phase is under way.
Why builders are being brought in now
Water Corporation has opened expressions of interest for what is known as early contractor involvement. Under that approach a construction contractor joins during design, before the main works are let, so that problems with building on a tight, working site are found on paper first.
"That process helps identify risks earlier, test different approaches and make better-informed decisions before major works begin." — Daniel Pastorelli, Water Minister
Mr Pastorelli said the approach would "help deliver better value for customers". Expressions of interest close on 1 December 2026, and the story was also reported by The West Australian on Wednesday.
Pipes before houses
The Subiaco announcement is the second of its kind in a week. On 18 November Water Corporation said the Government was spending $54.8 million on wastewater works in Treeby and Jandakot, including more than five kilometres of new pipeline and an upgrade that more than triples the capacity of the Clementine Boulevard pump station. That work is meant to open up around 3,500 residential lots in a 252-hectare area east of Solomon Road.
Both projects make the same point. New apartments around Subiaco and new estates in the southern suburbs cannot be connected until there is somewhere for the wastewater to go, and in the western suburbs that means a plant that turns 100 next year.
What happens next
Once expressions of interest close on 1 December, Water Corporation will choose a contractor to work with it on the design. The figures to watch for after that are the ones missing from this announcement: the full price of the upgrade, when construction would start, and what the odour control investigation recommends for the neighbours in Shenton Park and beyond.